Projects Map

Our water systems – underground, out of sight and out of mind – work 24 hours a day, seven days a week, 365 days a year, to bring reliable, high-quality water to the region.

We invest millions of dollars annually in infrastructure improvement projects to upgrade our water systems to provide for and protect the water supply and to meet drinking water standards. These infrastructure investments improve water quality, service reliability and water flows throughout our system.

Construction will take place from 7 a.m. to 4 p.m., Monday through Friday. See below for the projects scheduled for 2023-24 and details about the section of main to be replaced and the start date. All work will involve the replacement of water service lines in the public space, as needed, and the replacement of fire hydrants and valves.

Please consider enrolling in our CodeRED system, which we use to provide alerts about unexpected changes to project plans, including water service interruptions. Click here to learn more.


Water Main Replacements

2023-2024 Projects

 

Ansonia

Hawley Drive: The RWA will replace the existing water main on Hawley Drive from the intersection of Benz Street to the end of Hawley Drive as part of its Capital Improvement Program. These efforts will improve water quality and system reliability, and maintain adequate flows throughout the system. This work is scheduled to begin in June 2023 and is expected to take 12 to 14 weeks to complete.

Scope of Work

  • Installation of approximately 1,200 linear feet of water main
  • Replacement of water service lines in public space, as needed
  • Replacement of fire hydrants and valves, as needed

 

Branford

Flat Rock Road Extension: The RWA will replace the existing water main located on Flat Rock Road Extension from the intersection of Leetes Island Road and going north for 600 feet to end as part of its Capital Improvement Program. These efforts will improve water quality, system reliability and maintain adequate flows throughout the system. This work is scheduled to begin in September 2023 and is expected to take eight to 10 weeks to complete. 

Scope of Work

  • Installation of approximately 600 linear feet of water main
  • Replacement of water service lines in public space, as needed
  • Replacement of fire hydrants and valves, as needed

 

Leetes Island Road: The RWA will replace the existing water main located on Leetes Island Road from the intersection of Flat Rock Road Extension and going west for 400 feet to end as part of its Capital Improvement Program. These efforts will improve water quality, system reliability and maintain adequate flows throughout the system. This work is scheduled to begin in September 2023 and is expected to take eight to 10 weeks to complete. 

Scope of Work

  • Installation of approximately 400 linear feet of water main
  • Replacement of water service lines in public space, as needed
  • Replacement of fire hydrants and valves, as needed

 

Cheshire

Ott Drive: The RWA will replace the existing water main located on Ott Drive from the intersection of North Brooksvale Road to the Intersection of Sharon Drive as part of its Capital Improvement Program. These efforts will improve water quality, system reliability and maintain adequate flows throughout the system. This work is scheduled to begin in June 2023 and is expected to take 12 to 14 weeks to complete. 

Scope of Work

  • Installation of approximately 1,500 linear feet of water main
  • Replacement of water service lines in public space, as needed
  • Replacement of fire hydrants and valves, as needed

 

West Johnson Avenue: The RWA will install new water main located on West Johnson Avenue from the intersection of Dickerman Road going east for 700 feet and from the intersection of Marion Road going east for 800 feet as part of its Capital Improvement Program. These efforts will improve water quality, system reliability and maintain adequate flows throughout the system. This work is scheduled to begin in August 2023 and is expected to take 12 to 14 weeks to complete. 

Scope of Work

  • Installation of approximately 1,500 linear feet of water main
  • Installation of water service lines in public space, as needed
  • Installation of fire hydrants and valves, as needed

 

East Haven

Cortina Road: The RWA will replace the existing water main located on Cortina Drive as part of its Capital Improvement Program. Work will begin at the intersection of Jarden Drive and continue south to the intersection of Cortina Drive part running north and south. These efforts will improve water quality, system reliability and maintain adequate flows throughout the system. This work is scheduled to begin in September 2023 and is expected to take 10 to 12 weeks to complete. 

Scope of Work

  • Installation of approximately 900 linear feet of water main
  • Replacement of water service lines in public space, as needed
  • Replacement of fire hydrants and valves, as needed

 

Hamden

Carrington Street: The RWA will install water main on Carrington Street from the intersection of Savoy Street and going west for 400 feet to the intersection of Merrimac Street as part of its Capital Improvement Program. These efforts will improve water quality, system reliability and maintain adequate flows throughout the system. This work is scheduled to begin in January 2024 and is expected to take two to four weeks to complete.

Scope of Work

  • Installation of approximately 400 linear feet of water main
  • Replacement of water service lines in public space, as needed
  • Replacement of fire hydrants and valves, as needed

 

Milford and Orange

Country Lane: The RWA will replace the existing water main located on Country Lane in the towns of Milford and Orange as part of its Capital Improvement Program.  Work will begin at the intersection of West River Road, Milford and continue into the town of Orange and ending at the end of Country Lane. These efforts will improve water quality, system reliability and maintain adequate flows throughout the system. This work is scheduled to begin in June 2023 and is expected to take 12 to 14 weeks to complete.

Scope of Work

  • Installation of approximately 2,000 linear feet of water main
  • Replacement of water service lines in public space, as needed
  • Replacement of fire hydrants and valves, as needed